Walls Rising for New Moove-In Storage Units

UP GO THE WALLS – After weeks of preparing slab foundations on which new units will sit for the expansion of Moove-In Storage on East High Street in Sanatoga, masons this week were busy erecting block walls that are part of the structures. They were seen Wednesday (Aug. 31, 2022) assembling the 11th of what looked to be 17 or more courses of a wall on Moove-In’s east side. Contractors began preparing ground for the foundations in May. The work has begun to move more quickly as Moove-In owners look to meet a deadline set last September by members of the Lower Pottsgrove Zoning Hearing Board for completion of the project.

Walls Rising for New Moove-In Storage Units

Photos by The Post